March 31, 2003
Six Flags New Orleans had an 8 page insert in the Sunday Times Picayune. Check out images of the insert in the photo gallery.

March 30, 2003 - 1:30pm
The Times Picayune did an extensive article on the transformed Six Flags New Orleans. Check out the online article.

March 30, 2003
Saturday, March 29th was the first day for season pass processing. I have heard that lines were sporadic and almost non-existent. Much of this is probably due to minimal advertising by SFNO. I have posted some new pictures of the DC Comics Superheroes Adventure area which shows the progress of its construction. Judging from these photos, SFNO has a lot of work to do to get this area near completion by next weekend's grand opening. I believe they will get all the DC rides up and running though.

March 29, 2003 - 2:30pm
SFNO's newest water fountain is in Main Street Square (formerly the Jazz Fountain). The new fountain has dancing water effects and changes colors. Check out the video of the fountain in action.

March 29, 2003 - 12:30am
On Friday night, March 28th, Six Flags New Orleans hosted a private party for H&R Block employees and their families. All of the old rides were operating in Mardi Gras except for Krazy Krewe. A couple of rides in Cajun Country and Pontchartrain Beach were also operating. None of the new rides were in operation, but we did manage to get some GREAT photos of the new transformation, including Batman: The Ride, The Jester, the newly transformed Looney Tunes Adventure and more.

March 26, 2003
Six Flags New Orleans mailed out a flyer to previous pass holders and targeted customers advertising the transformed park and season passes. You can check out shots of the flyer in the photo gallery.

March 24, 2003
Season Pass vouchers went on sale today at Winn Dixie stores. They are $49.99 plus tax. Here is a shot of the front and back of the actual voucher you receive. These vouchers can be exchanged for a real Season Pass the first time you enter the park, or you can get them processed on one of three pre-season processing dates:

Saturday, March 29th - 12 to 6pm
Thursday, April 3rd - 5 to 9pm
Friday, April 4th - 5 to 9pm


March 23, 2003
Batman: The Ride will have at least one concrete trench similar to the final trench on the B:TR at Six Flags over Texas. Also, Joker's Jukebox is now being installed, along with the finishing touches on Catwoman's Whip and Lex Luthor's Invertatron.

March 22, 2003
Check out some Fun Facts about the transformation and expansion of Six Flags New Orleans on the news and rumors page.

March 21, 2003, 4:30pm
Check out the official ride names and new shows on the news and rumors page.

March 21, 2003, 11am
Construction at SFNO continues as opening day is only 15 days away. Check out the latest photos of the completed Jester track, Batman: The Ride's station construction, Lex Luthor's Invertatron, Catwoman's Whip and MegaZeph testing.

March 12, 2003
Jester is now complete through the second corkscrew and into the first part of the helix. Check out this report from WWL-TV's website for more information.

March 11, 2003
SFNO season pass processing dates have been added to the news and rumors page.

March 10, 2003
Two new interactive water fountains to be installed at SFNO. Check out the news and rumors page for more information.

March 9, 2003
Construction at SFNO continues at a rapid pace. Check out the photos of Jester, Batman: The Ride's station and the Lex Luthor's Invertatron (Zamperla Windshear) installation.

March 7, 2003
Jester trains, backwards or forwards? Muscial events, paddle boats and more on the news and rumors page.

March 5, 2003
Six Flags has changed the whole visual layout of all their sites, including Six Flags New Orleans. It still looks to be a work in progress. Click here to view the new official SFNO site.

March 4, 2003
Jester's lift hill is complete and the track continues almost to the edge of the first drop. Check out the latest photos of Jester.

March 2, 2003
Jester is rising rapidly. Now that Batman: The Ride's circuit is complete, the steel workers are concentrating their efforts on Jester's vertical construction. Check out the photos of Jester's almost completed lift hill.

March 1, 2003
Batman: The Ride's track is now finished. Look for testing in about a week or two. Also, Jester has now gone vertical. Check out the first photos of the completed B:TR circuit and Jester's vertical construction.